SR-134/HOLLYWOOD WAY RAMP IMPROVEMENT – BURBANK, CA

  • 3600’ UG – 35.5/12kV & 2 manholes
  • Construction completed in 2009.

I-5/HOV AND EMPIRE PROVIDENCIA – BURBANK, CA

  • 1880’ UG – 12/4 kV, 120’ – 36”Ø Jack & Bore & 8 manholes
  • Construction completed May, 2011.

I-5/HOV AND EMPIRE INTERCHANGE PROJECT – BURBANK, CA

  • 3500’ UG – 34.5/12kV
  • 18 UG manholes
  • Construction completed March, 2016.

EMPIRE INTERCHANGE PROJECT – NEW VICTORY BRIDGE – BURBANK, CA

  • 140’ through bridge cells – 34.5/12kV
  • 400’ UG
  • Construction in progress.

EMPIRE INTERCHANGE PROJECT – NEW BURBANK BRIDGE – BURBANK, CA

  • 300’ through bridge cells – 34.5/12 kV, 900’ UG & 3 manholes
  • Construction to Begin Spring 2017